CTC 260-Hydrology Schedule
January/February
|
Monday/Wednesday |
|
|
18 |
Hydrology: Overview & Definitions |
|
23/25 |
Watersheds: Characteristics & Delineation (Class canceled on Monday-weather) |
|
30/1 |
Precipitation/IDF Curves (assign Project 1) |
|
6/8 |
Hyetographs/Hydrographs |
|
13/15 |
Time of Concentration and Manning’s Equation |
|
20/22 |
Peak Flows (Rational Method) (assign Project 2) Project 1-IDF Due on Blackboard February 20 |
March
|
Monday/Wednesday |
|
|
27/1 |
Work on Project 2 (Flowmaster for checking pipe size) –submit first 2 lines on Wednesday |
|
6/8 |
Monday----- Review (topics:
delineations/drainage areas/hyetographs/hydrographs/unit
hydrographs/intensity/precipitation/IDF curves/frequency) Wednesday-----Midterm |
|
13/15
SPRING BREAK |
|
|
20/22 |
Peak Flows (TR-55 Method; Part 1) Project 2-Stormwater Design Due on Blackboard March 20 |
|
27/29 |
Peak Flows (TR-55 Method; Part 2) (assign Project 3) |
April/May
|
Monday/Wednesday |
|
3/5 Detention Design (Info needed to Route) Mon-Inflow Hydrograph/Storage; Wed-Orifice/Weirs |
|
10/12 Detention
Design (Routing) |
|
17/19 SWPPP Project 3-Peak Flows Due on Blackboard April 17 |
|
24/26 Work on Final Exam Project—detention basin design |
|
Final Exam Project 4 is due Wednesday
May 3rd at 10am (Blackboard dropbox) |