CTC 260 Projects

Project # 1 Develop IDF Curves   (Teams of 2 or Individual)

Using HYDRO-35 develop IDF curves (all on one graph) for the SUNY Poly Campus:

Gather data for the following frequencies and storm durations:

Storm Frequencies:  2, 5, 10, 25, 50 and 100 years

            Storm Durations: 5, 10, 15, 30, and 60 minutes

 

Using the NOAA Precipitation Frequency Server (https://hdsc.nws.noaa.gov/pfds/ ) get the data for the following frequencies and durations and place on an excel file.  Develop the 2nd IDF graph for the following frequencies and storm durations:

Storm frequencies: 2, 5, 10, 25, 50 and 100 years

Storm Durations: 1, 2 ,3, 6, 12 and 24 hours

 

Write up a “mini” report according to the following outline:

·         Cover Sheet (title, date, name, manhours-number of hours worked on project)

·         Method Using Hydro-35 (How did you develop or obtain the IDF curves using Hydro-35)

·         Sample Calculations for Hydro-35

·         Graphs of IDF Curves (two graphs; xy scatter (not line))—5 to 60 IDF curve (data from Hydro-35) and 1-24 hour IDF curve (data from precipitation server)

·         Summary (what did you learn, what areas you had problems with)

Drop off the report (electronic format----PDF) in the Brightspace dropoff box.

Project # 2 Design a Storm System (Team of 2 or Individual)

Download the project 2 excel file.   Compete the data and determine the pipe sizes needed.

Just drop off your final excel file in brightspace and do not write up a report.  

Note:  Use Flowmaster to check the pipe sizes.

 

Project # 3 Determine Peak Flows using the Rational and TR-55 Methods (Team of 2 or Individual)

 

An old USGS metric is here:  Metric USGS Map (1:24,000 scale or 1”=2000 ft; contour internal = 6 meters).  USGS map is here:  Newer Map (English version) 

Use the rational and TR-55 methods to determine the peak flows (2, 5, 10, 25, 50 and 100 year frequencies) on the unnamed creek.  The drainage area may be larger than what should be used for the rational method; however, try the rational method anyway for comparison and practice of using the method.

Instead of a formal report, prepare a short summary which includes the following:

·         Your Name and Date

·         Methods used

·         Figure showing watershed area

·         Table of peak flows summarizing both methods

·         Discuss the differences and possible sources for those differences

Resources:

Streamstats:  https://www.usgs.gov/streamstats

Web Soil Survey:  https://websoilsurvey.nrcs.usda.gov/app/

Precipitation Server:  https://hdsc.nws.noaa.gov/pfds/

 

Soil information---SUNY Poly Campus (not applicable to the culvert above but just FYI--------)

A 3-ring binder is kept by facilities showing boring data for each building and other projects done on campus.
There is data on about 100 or so borings.
Most terminate at 10 to 35 feet deep.
Some borings show a mixture of silt, sand, with small amounts of gravel down to 25 feet.
At that depth, we typically encounter some decomposed shale, glacial till, or an occasional boulder, but usually not bedrock.

Depth to groundwater varies significantly around the campus.
Up around the baseball field, I see readings as shallow as 2 feet on April of 1984.
Generally I would say GW is 15 to 20 feet for many locations.

Final Exam Project # 4 Design a Detention Basin (Team of 2 or Individual)

The location map is provided on Brightspace.

General steps:

1.    Calculate peak flow of non-developed tract (Rational Method)

2.    Calculate peak flow of developed tract (Rational Method)

3.    Calculate inflow hydrograph of developed tract (Asymmetrical Triangle) for purposes of routing

4.    Determine location of detention basin; provide a drawing showing the location on the given base map.

5.    By trial and error design a detention basin and outlet structure. (Hint: you can get a rough initial storage volume using TR-55 Chapter 6)

6.    Route the inflow hydrograph through the designed detention basin.  The routed outflow hydrograph should have the same peak flow (or lower) as the non-developed tract.

7.    Provide an engineering design report on your results according to the following outline:

Instead of a formal engineering design report include the following:

·         Your Name and Date

·         Introduction

·         Description of Existing Conditions (Provide Copy of Map)

·         Assumptions and Methods used

·         Detention Basin Design Description and Drawings (including Location on Map and Basin Drawings-preferably using CAD)

·         Summary Paragraph

·         Include other information:

·         Delineation of drainage area(s)

·         IDF Curve you used (use NOAA Precipitation Frequency Server)

·         Calculations (TR-55 Worksheet 3 for tc; Rational Method Calculations)

·         Calculations (Routing)

 

SUNY Poly Home | Baran's Classes | E-Mail S. J. Baran