CTC 260-Hydrology Schedule 

January/February

Tuesday/Thursday

20/22     

Hydrology:  Overview & Definitions

27/29 

Watersheds: Characteristics & Delineation 

3/5

Precipitation/IDF Curves

(assign Project 1-Develop IDF Curves)                    

10/12

Hyetographs/Hydrographs                            

17/19

Time of Concentration and Manning’s Equation     

24/26

Peak Flows (Rational Method)

(assign Project 2-Stormwater Pipe Size Design)

March

  Tuesday/Thursday

3/5

Tuesday----- Review (topics:  delineations/drainage areas/hyetographs/hydrographs/unit hydrographs/intensity/precipitation/IDF curves/frequency)

Thursday Midterm

10/12

Tuesday Kunsela A133; Thursday; Peak Flows (TR-55 Method; Part 1) (assign Project 3-Peak Flows using Rational Method and TR-55)

17/19 SPRING BREAK

24/26

Work on Project 3 (Due next Tuesday March 31)

April/May 

  Tuesday/Thursday

31/2 Detention Design (Info needed to Route) Tues-Inflow Hydrograph/Storage; Thurs-Orifice/Weirs

7/9 Detention Design (Routing) 

14/16 SWPPP-Stormwater Pollution Prevention Plan

21/23 Work on Final Exam Project; DRAFT due April 23.

28/30 Work on “Final Exam” Project---see due date below

  Final Online Exam Project Due Tuesday May 5 at 12:15 pm - Brightspace